Building a reliable, responsible supply chain that supports Goldboro from development through operations.
Design, supply, installation and operation (for both construction and operations phases) of the Employee Accommodations (EA) Facility including:
The EA Facility is to include the following features:
Design, supply and installation of modular Administration Offices (to initially be used for the construction management team).
Design, supply and installation of EA Facility and Administration Offices foundations suitable for the ground conditions (including timber cribbing, concrete footings, screw/helical piles, metal space frame, etc., as appropriate).
(The scope of SS001 Overall Site Services may be assigned to this contract.)
Construct haul and access roads and implement improvements to Gold Brook Road. This includes any required excavation, construction of subgrade and embankments, geotextile, geogrid, granular surfacing and berms, as well as installation of temporary silt fence, construction of permanent ditches along the roads as well as various culverts, clearing and grubbing.
Construct the Central, East and Southwest Settling Ponds. In addition to the construction of each pond, this includes the removal of watercourse (WC) WC-8 (with prior fish rescue by others), clearing and grubbing, installation of temporary silt fence, construction of permanent ditches around the three ponds and construction of pads for the Central and Southwest Impacted Water Treatment Systems (IWTS).
Construct the Employee Accommodations (EA) area and Outdoor Storage area. This includes clearing and grubbing for the EA area, Outdoor Storage area and Organic Stockpile OS#1, construction of the EA area and Outdoor Storage area pads including permanent ditches partially around each pad, construction of a temporary berm and permanent ditches partially around OS#1, installation of temporary silt fence in various areas, construction of a temporary pond, vehicle wash area / station and mud mat in the Outdoor Storage area.
Clear and grub the initial West Pit area including removal of WC-8 within the West Pit footprint (with prior fish rescue by others), construction of temporary ditches with three temporary sumps and pumps, and dewatering of the existing small pond within the West Pit footprint.
Clear and grub OS#3 and the East Pit area including removal of WC-11 and WC-12 within the East Pit footprint (with prior fish rescue by others), construction of temporary ditches around the East Pit with three temporary sumps and pumps, and construction of permanent ditches around OS#3.
Clear and grub the Southeast Waste Rock Storage Area (WRSA) and OS#4 including construction of temporary ditches partially around the Southeast WRSA and construction of permanent ditches around OS#4.
Clear and grub the Mill area (which includes the run-of-mine (ROM) area) and OS#10, level the Mill area pad, construct temporary ditches partially around the Mill area and permanent ditches around OS#10.
Clearing including:
Grubbing (the excavation and removal of tree stumps and roots to below the existing ground surface).
Bulk excavation of overburden, till and rock (including drilling and blasting of rock where necessary and haulage to the appropriate storage area).
Supply and installation of bulk backfill.
Supply and installation of liners for ponds and ditches.
Surface and ground water management and erosion/sediment control systems including excavation dewatering as well as stockpile dewatering.
Construction of any required temporary settling ponds in addition to those specified herein.
Temporary explosives supply and storage for rock blasting, if required.
Construct any haul and/or access roads not completed as part of the Early Earthworks contract. This includes any required excavation, construction of subgrade and embankments, geotextile, geogrid, granular surfacing and berms, as well as installation of temporary silt fence, construction of permanent ditches along the roads as well as various culverts, clearing and grubbing.
Clearing including:
Preparation of a reclaimed timber storage and removal plan
The removal and disposal of all trees, brush, underbrush, vegetative growth, logs, deadwood, debris, rubbish, and other objectionable matter down to natural ground level
Salvage of timber in accordance with the timber management regulations of the Province of Nova Scotia
Grubbing (the excavation and removal of tree stumps and roots to below the existing ground surface).
Bulk excavation of overburden, till and rock (including drilling and blasting of rock where necessary and haulage to the appropriate storage area).
Supply and installation of buried utilities including fresh water piping, fire water piping, propane piping, potable water piping, sewage piping, grounding grids, direct bury cables, duct banks, etc., as applicable.
Supply and installation of bulk backfill.
Supply and installation of liners for ponds and ditches.
Supply and installation of tailings and reclaim water pipelines including related earthworks, electric heat tracing and insulation, instrumentation, etc.
Supply and installation of any other overland pipelines including pit dewatering pipelines with electric heat tracing and insulation, instrumentation, etc.
Surface and ground water management and erosion/sediment control systems including excavation dewatering as well as stockpile dewatering.
Inspection, maintenance and operation of all erosion/sediment control systems installed as part of the Early Earthworks contract.
Construction of a concrete truck washout pond.
Construction of any required temporary settling ponds in addition to those specified herein.
Temporary explosives supply and storage for rock blasting.
Supply, installation and operation of a crushing and screening facility within the West Pit footprint to supply granular materials of various grades for this and other contracts. Relocate the crushing and screening facility as necessary to accommodate pit development.
Services include:
Services include:
Services include:
Design, supply and installation of temporary site 13.8 kV overhead power lines to laydown areas, construction management trailers, contractor trailers, various other site work areas, etc. and including, but not limited to:
Services include:
Detailed design, supply and installation of a collective and addressable, networked fire detection and alarm system comprised of:
Supply and installation of concrete foundations, grade walls, slabs on grade, pre-cast elements and other miscellaneous concrete structures including rebar and imbeds for the following areas:
Concrete will be sourced from nearby concrete production facilities.
Provide site services as part of the Sitewide Concrete Supply and Installation contract including:
Supply and installation of structural steel, mechanical and piping bulks and installation of mechanical equipment, plate and chute work and piping for the following areas:
Provide Mill Infrastructure area site services as part of the Process Plant SMP contract including:
Design, supply, fabrication and erection of various field erected tanks for the Process Plant.
Provide site services including:
Supply and installation of electrical and instrumentation bulks, as well as installation of electrical equipment and instrumentation for the following areas:
Power distribution within Mill Infrastructure area buildings and facilities (excluding overhead lines between buildings) including:
The scope items above include all interconnecting electrical and instrument cables, instrumentation, etc., as appropriate.
Provide Mill Infrastructure area site services as part of the Process Plant E&I contract including:
Supply and installation of Pre-Engineered Metal Buildings including:
Supply and installation of Modular Buildings including:
Supply and installation of Tension Fabric Buildings including:
Design, supply, equip, furnish and install a fully functioning (‘turnkey’) modular operational, metallurgical and environmental testing laboratory at the project site.
Services include:
Water Treatment Systems will be supplied by the Owner and will generally be modularized (‘sea cans’).
Services include:
Ground transportation services include:
Note: all buses to be equipped with functional vehicle monitoring systems.
Site-based (except where noted otherwise) Quality Assurance (QA) services including:
(may be divided into multiple contracts)
Site-based Quality Assurance services including:
Off-site Laboratory Quality Assurance services including:
Site security services including provision of Security personnel and resources to:
Site first aid and medical services include:
The above scope is to be adjusted to suit site personnel loading during the Early Works period.
Supply, install and maintain furnished and equipped office trailers, lunch rooms, wash cars, etc. for Integrated Project Management Team (IPMT) personnel including but not limited to:
(Number of required units and configuration(s) to be determined.)
Provide rapid courier services between the project site and various domestic and international locations for the IPMT personnel’s use
Waste and water management services include:
Note: all trucks to be equipped with functional vehicle monitoring systems
Site Services include:
The services listed above shall be provided across the project site.
(The scope of this contract may be assigned to CA250 Employee Accommodations Facility.)
Provide topographic and other surveying services across the project site to support Quality Assurance and other activities during construction. Services include:
Temporary fuel storage and dispensing services include:
Propane storage and dispensing services include:
Geotechnical services include construction phase field reviews and inspection services including, but not necessarily limited to:
Fish rescue services include:
Ornithology services include:
Services provider must have:
In the event that an archaeological or heritage resource is discovered as a result of site construction activities, collaborate with the Mi’kmaq Nation and Mi’kmaw communities and oversee an on-site precontact and historic artifact analysis, artifact conservation, artifact photography, etc.
The consultant for this package must hold a valid archaeological permit in the Province of Nova Scotia.
Training services include preparation, delivery and administration of site training programs including:
Training is expected to be a mix of virtual/online and in-person instructor-led programs.
(certain modules may be sub-contracted)
Spill remediation services including:
Commissioning support services include:
Logistics services for Owner-supplied equipment and materials including:
Logistics services for Owner-supplied equipment and materials including:
Website created by Explorationsites.com
Adam Larsen, P.Geo., Director of Exploration, of the Company, is considered a Qualified Person for the purposes of National Instrument 43-101 and has reviewed and approved the scientific and technical information contained on this website for matter relating to the Goliath Gold Complex.
Kevin Bullock, P. Eng., President, CEO and Director of NexGold, is a “qualified person” within the meaning of NI 43-101 and has reviewed and approved the scientific and technical information on this website for matters regarding the Goldboro Project.